Burlington ARUs: basement apartments and garden suites
How many additional units a Burlington lot can have, the size and setback limits for a backyard suite, parking, and the permits you need.
Summary
Burlington's Residential Zoning By-law 09-2026 permits up to three additional residential units on a parcel of urban residential land with a detached house, semi-detached house or townhouse, of which up to two may be detached units in one accessory building. A detached unit's building is limited to 80 square metres in most zones and 7 m in height with a peaked roof. Every new unit needs a zoning clearance through a Pre-Building Approval application, then a building permit.
Administered by the City of Burlington's Community Planning (zoning) and Building departments. Every answer below is checked against its source; the source and the date it was read are under each one. Last updated November 6, 2026.
What is allowed
What is an additional residential unit?
A self-contained living unit with its own kitchen, bathroom and sleeping areas, on the same property as a primary home: a single detached house, semi-detached house or townhouse. It can be inside or attached to the primary home, or in a separate accessory building such as a detached garage. The City's examples are basement apartments, attached suites, permanent tiny homes and coach houses.
Up to three, besides the main home. Zoning By-law 09-2026 permits up to three additional residential units on a parcel of urban residential land in all residential zones where a detached dwelling, semi-detached dwelling, street townhouse or rear lane townhouse is permitted. Up to two of the three may be detached units, and only one accessory building containing detached units is permitted per parcel.
The City cautions that not all properties will be able to have additional units; each application has to meet the zoning standards for the lot.
Can I add a unit on a rural property with a well or septic system?
No. The City's zoning handout says additional residential units are only permitted on a parcel of urban residential land, meaning land in a settlement area served by municipal sewage works and a municipal drinking water system. They are not permitted on properties with private water or sewer services, such as a well, cistern or septic system.
None for the first unit, and one parking space for each of the second and third. The City's ARU page says an application must also provide two parking spaces for the primary home. On the site plan, each space must be at least 2.75 m wide and 16.5 square metres in area and sit fully within the property boundaries.
Under Zoning By-law 09-2026, an accessory building containing a detached additional residential unit may have a gross floor area of up to 80 square metres, except in the LN5 and LN6 zones, where the maximum is 15 per cent of the lot area. Its maximum height is 7 m with a peaked roof or 6 m with a flat roof, and the roof may overhang a wall or post by no more than 0.5 m.
Maximum gross floor area
80 m² (15% of lot area in LN5 and LN6 zones)
Maximum height
7 m peaked roof, 6 m flat roof
Setback from interior side or rear lot line
1.2 m; 3 m for the part above 4.6 m (peaked) or 3.5 m (flat)
Setback from exterior side lot line
Same as the principal building's required exterior side yard
How close to the lot line can a backyard suite sit?
The building must be at least 1.2 m from an interior side lot line or rear lot line, and 3 m for any portion taller than 4.6 m with a peaked roof or 3.5 m with a flat roof. Toward an exterior side lot line it needs the same setback as the principal building. It must also be at least 4 m from the principal building on the same parcel.
Decks and balconies above the first storey and rooftop amenity areas are not permitted on or attached to the building, and exterior stairs above the first storey may not project into the front yard, exterior side yard or required interior side yard.
Yes, if its entrance is in the rear or interior side yard. A 1.2 m wide unobstructed pedestrian access must run from the street to the entrance of an attached or detached unit located there. A gate may be built within the access, but nothing may project into the 1.2 m width.
How do I find out whether my yard can fit a detached unit?
The City offers an interactive ARU look-up tool: enter your address for a high-level overview of how the property meets key zoning requirements for a detached unit, including lot size, building footprint and estimated buildable area. It is an initial assessment only; forestry, engineering and hydro reviews may further limit where a unit can go, and zoning staff must confirm what is permitted.
It is one of the forms the City supports. Its Garage Conversion Toolkit shows sample one-bedroom, two-bedroom and accessible layouts for attached and detached one-car and two-car garages, each with example floor plans and an estimated costing list. The renderings and plans are conceptual only and do not replace the architectural and other work needed to design a unit that suits your property and meets requirements.
Do I need a building permit for a basement apartment?
Yes. The City says you need a building permit for all new additional residential units and to legalize existing ones, and the unit must meet all applicable building and fire codes. To add one, two or three units you apply for a building permit for a renovation or addition to your house, or for an accessory building.
You must be the registered owner of the property. First submit a Pre-Building Approval application by email to zoning@burlington.ca, with drawings and, where needed, a tree permit and a grading and drainage certificate. Once you have your Zoning Clearance Certificate, email the provincial building permit application form and the ARU building checklist items to buildingpermits@burlington.ca with the project address in the subject line.
The City suggests working with a designer who holds a Building Code Identification Number (BCIN), or a modular manufacturer familiar with zoning and permit requirements.
The City's step-by-step guide gives these targets: staff check a Pre-Building Approval application for completeness within six business days; zoning review takes approximately two weeks for interior-only projects and three to four weeks for projects with exterior work; a building permit application is screened within two business days and the permit reviewed and issued within ten business days once the application is complete. Inspections are scheduled within two business days.
Pre-Building Approval completeness check
Within 6 business days
Zoning review, interior-only project
About 2 weeks
Zoning review, project with exterior work
About 3 to 4 weeks
Building permit screening
Within 2 business days
Building permit issued (complete application)
Within 10 business days
Start work within six months of getting the building permit. Schedule each required inspection with the inspector named on your permit, ending with the final inspection and your occupancy permit.
Contact Building staff at buildingpermits@burlington.ca. The City says they can help you work out whether the unit complies with the Ontario Building Code, the zoning by-laws and other regulations, check whether building and occupancy permits were ever issued, and explain what you need to do to legalize it if permits are missing.
Does Burlington pay homeowners to build an additional unit?
It has. The City's ARU Incentive Program, funded through the Housing Accelerator Fund, offered forgivable loans of up to $70,000 for each new affordable rental unit inside or attached to a house and up to $95,000 for a detached one, forgiven if the unit stayed affordable for 10 years, plus a one-time grant of up to $15,000 to legalize an existing unit and waivers of zoning clearance and building permit fees. The City's page says the program closed to applications on 1 October 2025.
Funding was first come, first served, and short-term rentals were not allowed in funded units. Check the City's incentive page for any new intake before budgeting on it.
Do development charges apply to an additional unit?
The City's incentive page flags one charge: education development charges may apply to detached additional residential units. They are set and collected by the local school boards, and were not eligible for waiver under the City's incentive program. Questions go to the Halton District School Board at 905-335-3663 or planning@hdsb.ca, or the Halton Catholic District School Board at 905-632-6300 or planning@hcdsb.org.