Burlington building permits: apply, timelines, fees

What needs a building permit in Burlington, what you need before you apply, how to submit, how long a decision takes and what happens after.

Summary

The City of Burlington issues building permits for construction, renovation and demolition under the Building Code Act; everything needs one except a listed set of small projects. Get your zoning clearance and grading approvals first, then email a complete application to buildingpermits@burlington.ca. For a house, the Building Code gives the City 10 days to issue or refuse a permit once the application is complete.

Check an issued permit on the City's building permit map · the official tool, for your own address

Administered by the City of Burlington's Building Department, under the Ontario Building Code Act and Building Permit By-law 30-2026. Every answer below is checked against its source; the source and the date it was read are under each one. Last updated November 16, 2026.


What needs a permit

Which projects do not need a building permit in Burlington?

The City lists the exceptions; everything else related to a building or structure needs a permit. Exempt projects include any structure under 10 square metres with no plumbing; one-storey detached sheds, garages, gazebos, carports and similar accessory buildings for a house under 15 square metres with no plumbing; detached pergolas; fences; on-grade patios without a roof; landscaping; retaining walls 1 m high or less; and a tent or group of tents of 60 square metres or less, not attached to a building and more than 3 m from other structures.

Any building or structure, no plumbing
Under 10 m² (108 ft²)
Detached accessory building for a house, one storey, no plumbing
Under 15 m² (161 ft²)
Detached uncovered deck for a house
Under 10 m² and under 60 cm above grade
Retaining wall
1 m (3.3 ft) high or less
Tents, not attached to a building
60 m² or less in total, more than 3 m from other structures
Ground-mounted solar collectors or dish antenna
Face area under 5 m² (54 ft²)

Exempt from a building permit does not mean exempt from zoning, the tree by-laws or the pool by-law, and the City does not issue electrical permits: contact the Electrical Safety Authority at 1-877-372-7233.

Source: City of Burlington, Building Permits, read November 16, 2026

Do I need a permit for a pre-built tiny house or backyard unit?

Yes, two. The City says building permits are required for structures built in one location and installed in another, and the process for a pre-built tiny house or additional residential unit has two stages: a permit for off-site construction, at the time the unit is partially constructed, and a second permit for on-site installation on your property. The City publishes separate checklists for each stage.

Source: City of Burlington, Building Permits, read November 16, 2026

Do I need a permit to demolish a building?

Yes. The Building Code Act says no person shall demolish a building unless the Chief Building Official has issued a permit. Follow the building permit application instructions with the provincial application form, the City's Demolition Clearance Form with its signatures and approvals, the drawings on the demolition checklist and the permit fee.

The City advises contacting the authorities whose services demolition may affect before work begins, such as Enbridge Gas for underground lines, and Forestry if a tree is to be removed. Page 3 of the clearance form lists them.

Source: City of Burlington, Demolition Permits, read August 24, 2026


Before you apply

What approvals do I need before applying for a building permit?

The City says you must have the necessary approvals and clearances for your site plan, zoning, and grading and drainage before you can apply: a site plan application where one is required, a zoning clearance certificate, and a grading and drainage clearance certificate. For residential projects these run through the Pre-Building Approval application handled by Community Planning.

If the property lies within Conservation Halton or Niagara Escarpment Commission boundaries, it is the owner's responsibility to contact them first: Conservation Halton at 905-336-1158, the Commission's Georgetown office at 905-877-5191.

Source: City of Burlington, Applying for a Building Permit, read August 16, 2026

Can I apply for a permit on a house I have not closed on yet?

No. The City says you must be the owner of the house before you can apply for a building permit, so wait until you take ownership. If you bought a house that the previous owner had under construction, apply for a transfer of permit by contacting the Building Department at 905-335-7731 or buildingpermits@burlington.ca.

Source: City of Burlington, Building Permits, read November 16, 2026

Can I draw my own plans, or do I need a designer?

As the owner you can. The Building Code gives a property owner an exemption to design buildings and structures on their own property, but the drawings must show enough detail to demonstrate that the project meets the Code's technical requirements: the standard expected is the same. Anyone else who prepares plans and takes responsibility for the design must be qualified and, where required, registered with the Province under a Building Code Identification Number (BCIN).

For most industrial, commercial and institutional construction a registered designer is not enough: drawings must be stamped by an architect, a professional engineer or both. The City does not recommend individual designers.

Source: City of Burlington, Building Permits, read November 16, 2026

Is there a checklist for my type of project?

Yes. The City publishes project-specific application requirements, and every required item must be in your package. Residential checklists cover accessory buildings, additional dwelling units, additions, basement finishing, decks and porches, demolition, interior renovations, new dwellings, sewage systems, site servicing, solar panel systems and tiny houses. Commercial, industrial and institutional checklists cover change of use, interior alterations, new construction, racking, tents and backflow prevention devices.

Source: City of Burlington, Applying for a Building Permit, read August 16, 2026


Applying, timelines and fees

How do I submit a building permit application?

By email only. Complete the provincial Application for a Permit to Construct or Demolish, prepare your drawings to the City's Electronic Application Submission Standards, and send the package to buildingpermits@burlington.ca with the subject line Building Permit Application followed by the project address, including any unit number. The City replies with next steps, including the fee and how to pay it.

Submissions that do not meet the electronic standards are not accepted, and a package over 20 MB needs a large file transfer, requested by email. For a re-submission, use the subject line Building Permit Re-submission with the application number and address.

Source: City of Burlington, Applying for a Building Permit, read August 16, 2026

How long does a building permit take in Burlington?

The Ontario Building Code sets the period within which a permit must be issued or refused once the application is complete: 10 days for a house where no dwelling unit sits above another and for a detached structure of up to 55 square metres serving it, and 15, 20 or 30 days for the other classes of building the Code defines, with retirement homes in the 20-day class and post-disaster buildings in the 30-day class. For home projects the City says a plan review is done within 10 business days, after which the permit is issued or you get a status report listing what must be addressed.

Houses, detached structures up to 55 m² serving them, tents, signs
10 days
Second class of buildings in the Code's table; farm buildings up to 600 m²
15 days
Third class of buildings; retirement homes; farm buildings over 600 m²
20 days
Post-disaster buildings and others the Code names
30 days

The clock applies to complete applications; an incomplete one is not accepted, and zoning clearance beforehand has its own review time.

Source: City of Burlington, Building Permit Turnaround Times (Ontario Building Code, Division C, Table 1.3.1.3), read August 29, 2025

How much does a building permit cost?

Fees are set in Schedule A of the City's Building Permit By-law, and the City emails you the amount once your application is accepted. The fee includes plan review and site inspection services, there is a minimum fee payable when you apply, and the City asks you to pay within two days of its response.

Before a permit is issued you may also be advised of other outstanding charges, such as parkland dedication, development charges and community benefits charges. Work started before a permit is issued attracts administrative penalty fees under the same schedule.

Source: City of Burlington, Residential Renovations and Additions, read August 14, 2026

What does a basement finishing application have to show?

The City's basement finish checklist asks for a scaled floor plan showing all room ceiling heights, dimensions, door sizes and uses; the location of smoke and carbon monoxide alarms; existing and proposed walls with framing, insulation, vapour barrier and finish; existing and proposed plumbing fixtures; supply, return and exhaust air openings; and the egress window's location and size if there is a bedroom in the basement.

That checklist is not for an additional dwelling unit, which has its own, and a pre-building approval from Community Planning comes first.

Source: City of Burlington, Basement Finish: Building Permit Application Checklist, read August 29, 2025


After the permit is issued

How do I look up a building permit for an address?

The City's interactive permit map shows issued permits, with active permits dating back five years, the assigned inspectors and their contact information. For a question about an active permit on the map, email buildingpermits@burlington.ca or contact the inspector named on the permit card. To check the status of an application that has not been issued yet, call 905-335-7731.

Source: City of Burlington, Building Permits, read November 16, 2026

What happens if work was done without a permit?

The City lists the consequences: administrative penalty fees under the building permit by-law; an order to comply or an order to stop work, either of which may be registered on title and affect your ability to refinance or sell; costly repairs or removal of work that does not meet the Building Code or other applicable law; costly inspections and engineers' reports; and possible fines and legal action against everyone involved. Section 36 of the Building Code Act sets maximum fines for a first offence of $50,000 for an individual or $500,000 for a corporation.

A permit also lapses if you wait: it may be revoked if construction has not begun within six months of issue.

Source: City of Burlington, Building Permits, read November 16, 2026

Sources

Every factual claim above traces to one of these documents.

  1. City of Burlington

    Building Permits

    Retrieved November 16, 2026

  2. City of Burlington

    Demolition Permits

    Retrieved August 24, 2026

  3. City of Burlington

    Applying for a Building Permit

    Retrieved August 16, 2026

  4. City of Burlington

    Residential Renovations and Additions

    Retrieved August 14, 2026

  5. City of Burlington

    Basement Finish: Building Permit Application Checklist

    Retrieved August 29, 2025