Skip to content

Business

Ontario put $5 million toward Tempel Canada's new Burlington transformer-core plant, which the company opened in June 2026

On August 4, 2026, the Province announced $5 million for what it called a $132-million Tempel Canada plant in Burlington. Parent company Worthington Steel had opened the 250,000-square-foot plant in June and puts its cost at about $85 million.

BurlingtonIQ Newsroom6 sources · 3 min read

Email

The details

What the Province announced on August 4

On August 4, 2026, the Ontario government said it was welcoming a $132-million investment by Tempel Canada, a subsidiary of Ohio-based Worthington Steel, to establish a new 250,000-square-foot manufacturing facility in Burlington. Tempel makes transformer cores and precision electrical steel laminations, the steel components at the heart of the transformers that move power through the electricity grid.

According to the Ministry of Economic Development, Job Creation and Trade, the investment sustains more than 200 existing positions and creates nearly 100 new jobs. The Province said the plant is equipped with robotics and real-time data diagnostics and will more than double Tempel's footprint in Canada. Ontario contributed $5 million through the Advanced Manufacturing and Innovation Competitiveness stream of its Regional Development Program. Ivan Meltzer, president of Tempel Steel, said in the release that the program "helped accelerate this investment in Burlington."

The Tempel Canada plant, from the Province's and the company's 2026 releases
Company
Tempel Canada, a subsidiary of Worthington Steel; incorporated in Burlington in 1996, according to FedDev Ontario
New facility
250,000square feet, in Burlington
Investment
$132 million, according to the Province; about $85 million, according to Worthington Steel
Jobs
More than 200 sustained and nearly 100 new, according to the Province
Provincial funding
$5 million, Regional Development Program, announced August 4, 2026
Earlier federal funding
$3.5 million from FedDev Ontario, announced March 3, 2025

The company says the plant opened in June

The provincial announcement came after the building was already running. In a release dated June 25, 2026, Worthington Steel said it had celebrated the opening of the new Tempel Canada facility in Burlington that week with a ribbon-cutting, facility tours, customers, employees and government officials. The company described the project as an investment of about $85 million that would create nearly 100 new jobs. Neither the Province nor the company explains the difference between the $132-million and $85-million figures.

Worthington Steel says its Burlington workforce has grown over the past decade from about 19 people to more than 220, and that its existing plant had reached its practical manufacturing capacity. It says more than 60 per cent of the new plant's capacity is already committed to customers, and that the plant adds amorphous transformer core manufacturing, a technology meant to reduce energy losses in transformers.

Government support for the expansion did not start with the Province. In March 2025, FedDev Ontario listed $3.5 million for Tempel Canada, a Burlington manufacturer, to expand its capabilities to meet growing demand for utility and industrial transformers.

Where things stand on November 10, 2026

The August 4 release is still the Province's only announcement on the project: a scan of everything the Ontario Newsroom published from July 9 to November 9, 2026 found no later release about Tempel. On the Environmental Registry of Ontario, a proposal posted on August 7, 2026 for a new air-and-noise approval for two production lines that anneal and laminate transformer cores at Tempel Canada's facility at 4741 Palladium Way remained at the proposal stage when checked on November 10; its comment period closed on September 21. The registry also shows an approval granted in June 2025 for a Tempel annealing and transformer-core facility at 5045 North Service Road.

  • Not stated in the documents read: which Tempel address is the new 250,000-square-foot building.
  • Not stated: when the nearly 100 new jobs will be filled, or whether the $5 million provincial contribution has conditions attached.

Sources

Every factual claim above traces to one of these documents.

  1. Province of Ontario

    Ontario Welcomes $132 Million Advanced Manufacturing Investment in Burlington

    Published August 4, 2026 · Retrieved November 10, 2026

  2. Worthington Steel

    Tempel Canada Opens New Manufacturing Facility

    Published June 25, 2026 · Retrieved November 10, 2026

  3. Worthington Steel

    Worthington Steel Expands Canada Operations

    Retrieved November 10, 2026

  4. Province of Ontario

    Tempel Canada Company - Environmental Compliance Approval (air), ERO 026-0829

    Published August 7, 2026 · Retrieved November 10, 2026

  5. Province of Ontario

    Tempel Canada Company - Environmental Compliance Approval (air), ERO 019-8793

    Published June 4, 2025 · Retrieved November 10, 2026

Spotted an error? We keep the URL, update the timestamp and record the change. Our corrections policy.


Go deeper

All stories