Halton Region approved $5.67 million to design six water projects for Aldershot, where about 4,500 homes are planned

On May 20, 2026, Regional Council funded planning and design for a pumping station and new watermains to serve Eagle Heights, the Taylor lands and 1200 King Road and to move North Aldershot off Hamilton's water supply. Construction money is to follow in 2027.

BurlingtonIQ Newsroom7 sources · 3 min read

Email

The details

What Regional Council decided

On May 20, 2026, Halton Regional Council approved $5,672,000 to advance six new water projects for the community of Aldershot, in the western part of Burlington near the Niagara Escarpment. The money pays for planning and design only. Regional staff said funding for construction would be brought to Council through the 2027 capital budget.

The report, No. PW-15-26, was approved without amendment as part of a motion covering the public works items on the agenda, and Council directed that a copy be sent to the City of Burlington.

Why the Region moved early

The report names three Aldershot development areas as a priority for the City of Burlington: Eagle Heights, the Taylor lands and 1200 King Road. All three are in the Region's 2023 Allocation Program. The allocation amounts to 941 single-dwelling equivalents and 594 infrastructure-dependent units, which the Region says represents about 4,500 residential units based on the housing mixes developers have proposed, and which would count toward Burlington's 2031 housing pledge.

Staff said the City had recently provided updated growth forecasts and development plans for these areas, and that design money was needed ahead of the 2027 budget to align infrastructure timing with the development approval process and reduce the risk of delays to the City's planning approvals.

There is a second purpose. The City of Hamilton currently supplies water to parts of Aldershot under the Halton-Hamilton Water Supply Agreement. The report says the updated servicing strategy is meant to increase resiliency in west Burlington and to let Halton serve the North Aldershot area independently of Hamilton's supply. The report says the wastewater strategy funded through the 2023 Allocation Program needed no additional infrastructure.

The six projects

Planning and design budgets, from Attachment #1 to Report No. PW-15-26
New pumping station, 2 million litres a day, at the new North Aldershot reservoir site
$1,696,000
Repurposing the Kingsway Booster Pumping Station
$946,000
New 600 mm watermain at the repurposed Kingsway station
$9,000
New 300 mm watermain on Kingsway Drive crossing Plains Road
$27,000
New 400 mm watermain on King Road crossing the Queen Elizabeth Way
$973,000
New 600 mm watermain on North Service Road from Kerns Road to King Road
$2,021,000
Total
$5,672,000

The six are among eight new water projects for Aldershot identified in the Region's Water, Wastewater and Transportation Integrated Master Plan. About 73 per cent of the cost is growth-related. Of the total, $2,165,000 comes from the residential development charges reserve, $1,955,000 is financed on an interim basis from the Region's revolving fund and is to be recovered from future development charges, and $1,552,000, the share not related to growth, comes from the Region's rate reserves.

The reservoir study

A new North Aldershot reservoir and pumping station had already been advanced through an earlier report to Council in March. In a memorandum to Council dated June 17, 2026, the commissioner of public works said the Region would begin a Schedule B Municipal Class Environmental Assessment study and preliminary design for the reservoir and pumping station in fall 2026. The May report had said that study would start in the spring.

The memorandum says the study will identify and compare possible sites, weighing capacity, feasibility, schedule, environmental impacts, property needs and cost, and that the public will be consulted through notices, a project webpage and a public information centre. A map attached to the May report labels the reservoir at 10 million litres.

Where things stand on November 10, 2026

As of November 10, Halton Region's list of environmental assessment studies has no entry for the North Aldershot reservoir and pumping station, and its media releases page includes no notice that the study has started. No site has been named and no public information centre has been announced. Construction funding has not yet been before Council; the report says it will be part of the 2027 budget and forecast.

Sources

Every factual claim above traces to one of these documents.

  1. Halton Region

    Report No. PW-15-26 - Aldershot Water Servicing

    Published May 20, 2026 · Retrieved November 10, 2026

  2. Halton Region

    Attachment #1 to Report No. PW-15-26: Capital Budget & Financing Plan

    Published May 20, 2026 · Retrieved November 10, 2026

  3. Halton Region

    Attachment #2 to Report No. PW-15-26: Community of Aldershot Proposed Water Infrastructure Program

    Published May 20, 2026 · Retrieved November 10, 2026

  4. Halton Region

    Regular Meeting of Regional Council 06-26 - Minutes, May 20, 2026

    Published May 20, 2026 · Retrieved November 10, 2026

  5. Halton Region

    Municipal Class Environmental Assessment Studies

    Retrieved November 10, 2026

  6. Halton Region

    Media Releases

    Retrieved November 10, 2026