Burloak Drive underpass: the new rail bridge went into service in June 2026, with excavation still to come
Metrolinx scheduled a 10-day closure of Burloak Drive from May 22, 2026 to bring tracks into service on the new rail bridge between Burlington and Oakville. Road widening began October 20; no date is published for the underpass to open.
The details
What happened in May and June
On May 19, 2026, Metrolinx announced that a section of Burloak Drive in Burlington and Oakville would close for 10 days so that train tracks could be brought into service on the newly built Burloak rail bridge. Its construction notice scheduled the closure from 12:01 a.m. on May 22 to 6 a.m. on June 1, between the Harvester Road/Wyecroft Road intersection and the Prince William Drive/Superior Court intersection, covering the road, the sidewalk and the bike lane.
Metrolinx said a full closure was needed while crews installed grade-crossing equipment such as signal arms, which would not be operational until all tracks had been shifted onto the bridge. Crews were also to relocate and pave the railway crossing on the temporary detour road and install storm sewers south of the Harvester/Wyecroft intersection. The agency's project page now lists the milestone "New rail bridge deck in service" under June 2026.
Done: Contract awarded
February 2022. Early works construction started in March 2023.
Done: Temporary track diversion and detour road
Track diversion built in June 2024; the temporary detour road opened in May 2025.
Done: New rail bridge
Concrete poured for the bridge deck in November 2025; track construction in April 2026; deck works completed in May 2026; in service June 2026.
Now: Coming up on site
Utility relocations, bulk excavation for the underpass and the remaining storm sewer works. Road widening, under a separate October notice, is also under way.
Next: Future milestones
Completion of underpass excavation and storm sewers, opening of the underpass to vehicle traffic, then project completion and handover. Metrolinx lists no dates.
What the project is
The grade separation is a rail-over-road underpass: Burloak Drive will pass beneath the Lakeshore West tracks instead of crossing them at street level. Metrolinx is building it with the City of Burlington and the Town of Oakville as part of GO Expansion, which is intended to give the Lakeshore West line the capacity for trains every 15 minutes or better. The project also widens Burloak Drive to make room for on-street bicycle lanes and a multi-use path on both sides, with the possibility of going from four vehicle lanes to six in the future. It also widens the intersection at Superior Court and Prince William Drive. The City of Burlington's project page says that once 15-minute all-day service runs on Lakeshore West, up to eight trains an hour will cross Burloak Drive, in addition to VIA and freight trains.
Work since the bridge went into service
- August 24 to 28, 2026: the dates Metrolinx's notice set for repaving Burloak Drive from south of Prince William Drive to New Street, with closures of two to three days each at the Flora Drive intersection and then the Adele Road and Fothergill Boulevard intersections.
- From October 20, 2026: work on the curbs, sidewalks and roads for the future Burloak Drive, Superior Court and Prince William Drive. Metrolinx says the widening is split into five stages and began with the west side of Burloak just north of Prince William Drive.
- Ongoing: recurring short-term lane closures between the Rebecca/New Street and Harvester/Wyecroft Road intersections.
Where things stand on November 10, 2026
Metrolinx describes the project as in construction. Its October 19 notice gives the current road widening an expected duration of October 20 to December 18, 2026, weekdays from 7 a.m. to 5 p.m. Two-way traffic is being maintained, short-term sidewalk closures with signed detours are expected, and Metrolinx anticipates no impact on transit service.
What Metrolinx has not published is a date for the underpass to open to vehicles or for the project to finish; both appear on its project page only as undated future milestones. The City of Burlington's own project page, dated October 29, 2026, does not settle it: its schedule line reads "Ongoing to end of 2027", while the text below still says the project is estimated to be completed by mid-2026. Questions go to Metrolinx's Halton community engagement team at 416-202-1519 or HaltonRegion@metrolinx.com.