June 23, 2026: Burlington Council started an Official Plan review and widened 1200 King Rd. plans to include an arena
Council told staff to begin reviewing the City's Official Plan, with a special meeting to launch it in early 2027, and endorsed an event centre, a community centre and a recreational ice facility as the facilities to study for 1200 King Rd.
The details
An Official Plan review for 2027
At its regular meeting on June 23, 2026, Burlington City Council directed staff to begin a review of the City's Official Plan under section 26 of the Planning Act, the provision that requires municipalities to review their plans periodically. According to the City's summary of the meeting, staff are to schedule a special meeting of Council in the first quarter of 2027 to formally start the review. Council endorsed the public engagement approach in an appendix to staff report DGM-23-26, and authorized staff to commission specialized technical work and peer-review support up to $100,000, paid from the Policy Reserve Fund.
The same decision withdrew certain Major Transit Station Area policies and schedules from the Burlington Official Plan, 2020, as identified in another appendix to the report. The City's summary does not list which policies were withdrawn, and the report itself could not be read, so the effect on the three GO station areas is not reported here. The review will be carried out by the Council elected on October 26, 2026.
1200 King Road: an arena and community centre on the list
Council endorsed an updated list of community facilities under consideration for the 1200 King Rd. development, the planned urban village that Council approved in July 2026 and whose Official Plan amendment is now under appeal. The list, from report CAO-01-26, is:
- an event centre (arena);
- a community centre with aquatics and/or basketball facilities;
- a recreational ice facility;
- conference and multi-purpose space;
- a parking facility.
Council sent staff into a detailed due-diligence phase: confirming capital costs and operating models, negotiating with possible partners, funders and operators, weighing financing options including tax increment financing and money from other governments, and building a business case and funding strategy. Staff are to aim to report back in the second quarter of 2027 with a recommended funding strategy, partnership model and implementation plan before any capital or financial commitment is made. Council also acted on a confidential appendix, whose contents were not released.
Downtown parking and other decisions
Council directed staff to hire a consultant for a market feasibility analysis of future public off-street parking in the downtown core, including whether more capacity is needed before 2030, how it could be funded and who might partner on it. The study's cost was referred to the 2027 budget, to be paid from the Downtown Parking Growth Reserve Fund if approved. The same meeting approved the $150 windrow-clearing fee model, asked for reports on cricket in Central Park and on construction hours, received the 2027 financial forecast, and sent the City's opposition to the Millcroft Greens zoning-order request to the province; each of those is reported separately on this site.
Where things stand on November 11, 2026
The City's news feed, checked on November 11, 2026, has not announced a date for the special meeting to start the Official Plan review or any public report on the 1200 King Rd. facilities since June. Both decisions will come to the Council elected on October 26, 2026.
Sources
City of Burlington
June 23, 2026 Burlington City Council Decision Highlights and Updates