Six provincial highway projects are listed for Burlington through 2029, led by QEW/403/407 interchange bridge work

The Province's 2026–2029 Southern Highways Program, published in August 2026, lists bridge rehabilitation at the QEW/403/407 and Fairview Street interchanges, now under way with a 2029 target, and resurfacing of the QEW and Highway 403 from 2027.

BurlingtonIQ Newsroom4 sources · 3 min read

Email

The details

What the program lists

In August 2026 the Ministry of Transportation published its 2026–2029 Southern Highways Program, the table of provincial highway projects that are planned or under way. The program file is dated August 7, 2026, and the Province's highway programs page was updated on August 14. Six of its rows give Burlington as the location. All six are rehabilitation projects, meaning repairs to existing bridges, culverts and pavement, rather than new lanes or interchanges.

Burlington projects in the 2026–2029 Southern Highways Program (start year, status, target completion, estimated cost range)
Highway 403, King Road underpass
Bridge rehabilitation. Start year 2024, under way, target 2026. $0 to $10 million. Contract 2024-2031
QEW/403/407 and Fairview Street interchanges, Phase 2
Bridge rehabilitation over 8.1 km. Start year 2026, under way, target 2029. $50 million to $100 million. Contract 2025-2011
Highway 403, Waterdown Road and Lemonville Road
Bridge rehabilitation. Start year 2027, planned, target 2028–2029. $0 to $10 million. Contract 2025-2013
QEW, Guelph Line to Third Line
Resurfacing over 19.5 km. Start year 2027, planned, target 2028–2029. $25 million to $50 million
Highway 403, "QEW/403/407 interchange Guelph Rd. to Hwy 6"
Resurfacing over 17.0 km. Start year 2027, planned, target 2028–2029. $25 million to $50 million. Contract 2024-2017
QEW/403/407 (Freeman interchange), Phase 3
Bridge and culvert rehabilitation over 8.1 km. Start 2028–2029, planned, target "not available". $50 million to $100 million

The two projects already marked as under way have completed designs. The four planned projects are listed with design under way, and all six are listed as design-bid-build contracts. The Province's data guide explains two of the labels: an under-way project shows its scheduled end year, and a target of "not available" means a project scheduled to be completed in 2030 or later, which is how the third phase of the Freeman interchange work is listed.

How much is being spent

The Province gives ranges rather than contract prices. Added together, the six Burlington rows span $150 million to $320 million. The largest are the two interchange phases at $50 million to $100 million each. Province-wide, Ontario says it is committing about $5.4 billion to repair and expand provincial highways and bridges between April 2026 and March 2027, including about $2.1 billion of construction funding in southern Ontario.

Next door: the Highway 5 and 6 interchange in Waterdown

The same program lists a new interchange at Highway 5 and Highway 6 in Hamilton as a 2026 expansion project costing $100 million to $250 million. On October 30, 2026, the Ministry announced that construction had started. A new bridge will carry Highway 5 over Highway 6, with new on- and off-ramps, replacing the existing intersection in Waterdown. The project also widens a section of Highway 5 to six lanes and adds a commuter parking lot and multi-use paths. GIP Paving Inc. holds the contract.

Drivers in Hamilton and Burlington know how frustrating it can be to sit in traffic at Highways 5 and 6 in Waterdown.
Prabmeet Sarkaria, Minister of Transportation, in the Province's October 30, 2026 release

Where things stand on November 10, 2026

The August program is still the current one: on November 10, 2026 the Province's highway programs page, last updated August 14, carried the same Southern Highways Program file, with a note that the tables reflect information as of May 29, 2026. That note also says the timing of projects is subject to change based on funding, planning approvals, design, property acquisition and construction requirements, and that costs may change.

  • Not in the program: which lanes, ramps or bridges close, and on what dates.
  • Not in the Waterdown release: a completion date for the interchange. The program lists its target completion as "not available", the label for 2030 or later.
  • Not listed for Burlington: any expansion project. None of the program's widening or new-highway rows names the city.

Sources

Every factual claim above traces to one of these documents.

  1. Province of Ontario

    2026-2029 Southern Highways Program

    Published August 7, 2026 · Retrieved November 10, 2026

  2. Province of Ontario

    Ontario's highway programs

    Retrieved November 10, 2026

  3. Province of Ontario

    Ontario's Highway Programs Data Guide

    Published August 12, 2026 · Retrieved November 10, 2026

  4. Province of Ontario

    Ontario Starting Construction on New Interchange in Waterdown

    Published October 30, 2026 · Retrieved November 10, 2026

Spotted an error? We keep the URL, update the timestamp and record the change. Our corrections policy.