Shed permits in Burlington: size, setbacks, fees

When a shed, gazebo or detached garage needs a building permit in Burlington, the zoning limits on where it can go and how tall it can be, and what applying costs.

Every answer sourcedAdministered by the City of Burlington's Building Department (building permits) and Community Planning Department (zoning and pre-building approval). Every answer below was checked against its source on November 27, 2026; the source is linked under each one.

The short answer

A Burlington shed or other detached accessory building needs a building permit if it is bigger than 15 square metres (161 square feet), taller than one storey, attached to another building, or has plumbing. Every shed must meet the zoning by-law even without a permit: in residential zones under By-law 09-2026, at least 0.6 metres from the rear and side lot lines, at most 4.6 metres high with a peaked roof, and not in the front yard.

Last verified

The official tool answers for your own address. From 10 official sources, administered by the City of Burlington's Building Department (building permits) and Community Planning Department (zoning and pre-building approval).

Do I need a permit?

3 questions
  1. Do I need a building permit for a shed in Burlington?

    Only above the City's limits. You must get a building permit before starting construction if the shed or accessory building is bigger than 15 square metres (161 square feet) in gross area, is taller than one storey whatever its size, is attached to another building or structure, or contains any plumbing whatever its size. A detached, one-storey shed of 15 square metres or less with no plumbing needs no building permit.

    Watch for: The City says a shed must comply with the applicable zoning by-law even when no building permit is needed. To confirm whether yours needs a permit, email the Building Department at buildingpermits@burlington.ca or call 905-335-7731.

    Source: City of Burlington, Sheds and Accessory Structures

  2. What small structures are exempt from a building permit in Burlington?

    The City's exemption list includes any building or structure under 10 square metres (108 square feet) with no plumbing, regardless of height, and detached accessory buildings for a house, such as sheds, gazebos, garages, carports, greenhouses or solariums, cabanas and shipping containers, of one storey and under 15 square metres (161 square feet) in gross area, with no plumbing. Detached pergolas and detached outdoor fireplaces for a house are also exempt.

    Watch for: Here a house means a detached house, semi-detached house or row house with no more than two dwelling units. The City notes that open-air burning rules may still apply to an outdoor fireplace.

    Source: City of Burlington, Building Permits

  3. What counts as an accessory building?

    The City describes accessory buildings as detached from other buildings and on the same lot, used with the main house. They include sheds, gazebos, garages, carports, greenhouses or solariums, cabanas, shipping containers and similar structures.

    Watch for: Whether or not it needs a building permit, an accessory building must comply with the applicable zoning by-law. To confirm whether yours needs a permit, ask the Building Department.

    Source: City of Burlington, Sheds and Accessory Structures

Zoning: where it can go and how big

4 questions

Burlington has two zoning by-laws in effect. Which one covers your lot decides the setbacks and height.

  1. Which zoning by-law applies to my property?

    The City says two zoning by-laws are in effect: Residential Zoning By-law 09-2026, which came into force on March 2, 2026 and applies only to the residential zoned areas on its maps (the Low-Rise Neighbourhood zones LN1 to LN8 and the High-Rise Neighbourhood zone HN), and Zoning By-law 2020, which still applies elsewhere. Look up your property on the City's interactive zoning map, and the City asks you to verify zoning designations and regulations with its zoning staff if you are planning a project.

    Watch for: If a shed cannot meet the zone's rules, the City says you need a Zoning By-law amendment or a Committee of Adjustment application.

    Source: City of Burlington, Zoning

  2. How far from the property line must a shed be under By-law 09-2026?

    In a residential zone under By-law 09-2026, an accessory building or structure must be at least 0.6 metres from the rear lot line and from an interior side lot line, and as far from an exterior side lot line as the house must be. It may not be in a front yard or a required exterior side yard. The roof may overhang a wall or post by at most 0.5 metres, and it may be at most 4.6 metres high with a peaked roof or 3.5 metres with a flat roof.

    Residential Zoning By-law 09-2026, Table 1: accessory buildings and structures

    Checked
    Residential Zoning By-law 09-2026, Table 1: accessory buildings and structures
    RuleRequirement
    Minimum setback to the rear lot line0.6 m
    Minimum setback to an interior side lot line0.6 m
    Minimum setback to an exterior side lot lineSame as the minimum exterior side yard for the house
    Maximum roof overhang from a wall or post0.5 m
    Maximum height, peaked roof4.6 m
    Maximum height, flat roof3.5 m
    LocationNot in a front yard or required exterior side yard
    Floor area of each accessory buildingNo more than 10% of the lot area, counted in lot coverage
    UseNot for habitation, except as a detached additional residential unit

    A detached additional residential unit follows Table 2 of the by-law instead.

    Table source: City of Burlington, Residential Zoning By-law 09-2026, Part 5: General Provisions (October 2026)

    Watch for: Each accessory building's floor area counts toward the zone's maximum lot coverage and may not exceed 10 per cent of the lot area. Under Section 5.44, an accessory building of 15 square metres or more must also be at least 6 metres from the floodplain, meander belt or top of bank of a watercourse, unless Conservation Halton permits less.

    Source: City of Burlington, Residential Zoning By-law 09-2026, Part 5: General Provisions (October 2026)

  3. What are the shed rules under Zoning By-law 2020?

    For buildings accessory to a detached, semi-detached, duplex, triplex, fourplex or street townhouse dwelling, Zoning By-law 2020 has two sets of rules. One of up to 10 square metres needs no minimum setback from interior lot lines but must be 7.5 metres from a side lot line on a street, 90 cm from a rear lot line on a street and 15 metres from the front lot line, and at most 2.5 metres high. A larger or taller one is allowed only in the rear yard, 1.2 metres from the rear and side lot lines, one storey, at most 50 square metres, and 4.6 metres high with a peaked roof or 3.5 metres with a flat roof.

    Zoning By-law 2020, Subsection 2.2.1: buildings accessory to houses

    Checked
    Zoning By-law 2020, Subsection 2.2.1: buildings accessory to houses
    RuleUp to 10 m² floor areaOver 10 m² or over 2.5 m high
    Where on the lotAt least 15 m from the front lot linePermitted in a rear yard; not in a front, street side or required side yard
    Setback from a rear lot lineNo minimum (90 cm where it abuts a street)1.2 m
    Setback from a side lot lineNo minimum (7.5 m where it abuts a street)1.2 m (7.5 m from a street side yard)
    Maximum height2.5 m4.6 m peaked roof, 3.5 m flat roof, one storey
    Maximum floor area10 m²50 m²
    Maximum roof overhang from a wallNot stated0.5 m

    The dividing wall of a semi-detached garage may be built on the side lot line.

    Table source: City of Burlington, Zoning By-law 2020, Part 1: General Conditions and Provisions (May 2026)

    Watch for: Under By-law 2020, accessory buildings may not be built of concrete or masonry blocks unless the blocks are decorative or covered with stucco or siding with a permanent colour finish.

    Source: City of Burlington, Zoning By-law 2020, Part 1: General Conditions and Provisions (May 2026)

  4. How does the City measure a shed's size, height and setbacks?

    The City's zoning checklist for By-law 09-2026 asks for setbacks measured perpendicular to the property lines from the closest point of the building, floor area measured to the outside edge of the exterior walls or posts, overall height measured from the top of the building to the lowest point of the surrounding grade, and roof overhang measured from the wall or post to the outside roof edge, including the eavestrough. Drawings must be in metric.

    Watch for: Lot coverage is not required for pergolas or open-roofed structures. The checklist also says residential play equipment, planters, flagpoles, garden ornaments, fences, pools, hot tubs and patios less than 0.6 metres above grade are not structures for zoning purposes.

    Source: City of Burlington, Zoning checklist and FAQ for Low-Rise Neighbourhood for By-law 09-2026

Applying, fees and timelines

7 questions
  1. What approval do I need before applying for a shed permit?

    A Pre-Building Approval from the City's Community Planning Department, its written confirmation of the zoning, forestry and grading and drainage rules for your property. Download and complete the application form and email it to zoning@burlington.ca; staff check it for completeness and review it at a weekly pre-screen meeting, then give you a file number and the fees. Since January 1, 2025, for a one-storey accessory building you may apply for the building permit before the Zoning Clearance Certificate is issued.

    Watch for: The City says approval may take up to 4 to 6 weeks because of current volumes. Track your file in the myfiles portal; once you have your tree permit, if one is needed, you may start construction.

    Source: City of Burlington, Pre-Building Approval Application

  2. What do I need to submit for a shed building permit?

    The City's checklist for accessory buildings asks for the provincial Application for a Permit to Construct or Demolish, schedules showing the designer's qualifications, and construction drawings to scale: a site plan or property survey showing the shed's location and its setbacks from the property lines, a plan view with dimensions, framing and roof slope, elevations of all sides with openings and finished height, a cross-section of the footing, foundation, wall and roof construction, and truss drawings sealed by a professional engineer if you use manufactured trusses.

    Watch for: As the owner you may draw your own plans without being qualified under the Building Code, as long as they show the project complies; anyone else who designs it needs the required qualifications. Applications are emailed to buildingpermits@burlington.ca and must meet the City's electronic submission standards.

    Source: City of Burlington, Accessory Buildings for Residential Houses: Building Permit Application Checklist

  3. How much does a shed permit cost in Burlington?

    Under Schedule A of Building Permit By-law 030-2026, a residential accessory building (shed) is charged the minimum permit fee, $377.00, which the schedule sets as a flat fee. Permit fees are rounded to the nearest dollar, and paying them does not exempt anyone from complying with the Building Code Act, the Building Code or other applicable law.

    Watch for: HST is charged where applicable. The City's accessory building checklist says you will be told of any other outstanding fees, such as parkland, development or community benefits charges, before the permit is issued.

    Source: City of Burlington, Schedule A to Building Permit By-law 030-2026: Classes of Permits and Fees

  4. What does the zoning clearance for a shed cost?

    Under the City's 2026 zoning fees, effective January 1, 2026, a Zoning Clearance Certificate for a residential basement finish, deck, porch or accessory building is $400.00. If your drawings need revising more than twice, a revision fee of $680.00 applies to the third and each later submission.

    Zoning clearance, residential accessory building
    $400.00
    Revision, third and later submissions
    $680.00

    Source: City of Burlington, 2026 Zoning Fees

  5. How long does a shed permit take, and are there inspections?

    The City says a plan review is done within 10 business days of submitting your building permit application; at that point the permit is either issued or you get an application status report listing what must be fixed first. Once the permit is issued you receive a checklist of the inspections needed, and you book them directly with the building inspector named on your permit card.

    Source: City of Burlington, Sheds and Accessory Structures

  6. Do I need any approvals besides the City's?

    Possibly. The City says other regulatory approvals may be needed if your property is within Conservation Halton or Niagara Escarpment Commission boundaries, and it is the owner's responsibility to contact those agencies to find out their requirements. Conservation Halton can be reached at 905-336-1158 and the Niagara Escarpment Commission at 905-877-5191.

    Source: City of Burlington, Sheds and Accessory Structures

  7. What happens if I build a shed that needed a permit without one?

    The City lists the consequences: administrative penalty fees under the Building Permit By-law, an order to comply or a stop-work order that may be registered on title and affect refinancing or selling, costly repairs or removal of work that does not meet the Building Code or other laws, engineers' inspections and reports, and possible fines and legal action. Under the Building Code Act, the maximum fine for a first offence is $50,000 for an individual or $500,000 for a corporation.

    Watch for: You must own the house before you can apply for a building permit in Burlington.

    Source: City of Burlington, Building Permits

Official sources and contacts

10 official pages
The official toolLook up your property's zoning (City of Burlington map)The official tool, for your own address. Its answer is the one that counts.Open experience.arcgis.com
Who to contact
Building Department (building permits)
905-335-7731 · buildingpermits@burlington.ca
Community Planning Department (zoning, pre-building approval)
905-335-7642 · planning@burlington.ca

Sources

  1. City of BurlingtonSheds and Accessory StructuresRetrieved November 27, 2026
  2. City of BurlingtonBuilding PermitsRetrieved November 27, 2026
  3. City of BurlingtonZoningRetrieved November 27, 2026
  4. City of BurlingtonResidential Zoning By-law 09-2026, Part 5: General Provisions (October 2026)Retrieved November 27, 2026
  5. City of BurlingtonZoning By-law 2020, Part 1: General Conditions and Provisions (May 2026)Retrieved November 27, 2026
  6. City of BurlingtonZoning checklist and FAQ for Low-Rise Neighbourhood for By-law 09-2026Retrieved November 27, 2026
  7. City of BurlingtonPre-Building Approval ApplicationRetrieved November 27, 2026
  8. City of BurlingtonAccessory Buildings for Residential Houses: Building Permit Application ChecklistRetrieved November 27, 2026
  9. City of BurlingtonSchedule A to Building Permit By-law 030-2026: Classes of Permits and FeesRetrieved November 27, 2026
  10. City of Burlington2026 Zoning FeesRetrieved November 27, 2026

Every answer on this page traces to one of these documents.

Last checked 10 official pages from City of Burlington