Major road projects in Burlington

The multi-year road, bridge and highway projects in Burlington that have an official project page: what each is, where, its status and timeline as stated, and the traffic impact.

Every answer sourcedAdministered by The City of Burlington, Halton Region, Metrolinx and the Ontario Ministry of Transportation, each for its own projects. Every answer below was checked against its source on November 26, 2026; the source is linked under each one.

The short answer

Metrolinx's Burloak Drive underpass is under construction, with completion estimated by the end of 2027, the City says. Halton Region is widening Dundas Street from four to six lanes in stages, with the Guelph Line to Kerns Road section expected to start in late 2026, and the Province lists QEW and Highway 403 bridge and resurfacing work in Burlington through 2029. Each timeline is as its owner stated it on November 26, 2026.

Last verified

From 6 official sources, administered by The City of Burlington, Halton Region, Metrolinx and the Ontario Ministry of Transportation, each for its own projects.

Major multi-year projects

3 questions
  1. When will the Burloak Drive underpass be finished?

    The City of Burlington says construction is underway on Metrolinx's Burloak Drive grade separation and the project is estimated to be completed by the end of 2027. The project builds an underpass so Burloak Drive passes under the Lakeshore West rail line, adding turn lanes, sidewalks and bike lanes. Metrolinx says the widened road will have on-street bicycle lanes and a multi-use path on both sides, with room to expand from four to six lanes in the future.

    Watch for: Short-term Burloak Drive closures and detours are posted as notices; see the road closures guide.

    Source: City of Burlington, Metrolinx Burloak Drive Underpass

  2. What is happening with the Dundas Street widening in Burlington?

    Halton Region is widening Dundas Street from four to six lanes, with new multi-use paths and sidewalks, upgraded stormwater infrastructure, new traffic signals and street lights. Construction on the section from Appleby Line to Tremaine Road started in spring 2021, and the Region anticipates completing Phase 1 (Appleby Line to Bronte Road) in 2027. Within Burlington, the Guelph Line to east of Kerns Road section has an anticipated construction start of late 2026, and the Appleby Line to Northampton Boulevard and Northampton Boulevard to Guelph Line sections early 2028.

    Appleby Line to Tremaine Road
    Construction started spring 2021
    Guelph Line to east of Kerns Road
    Anticipated construction start late 2026
    Appleby Line to Northampton Blvd.
    Anticipated construction start early 2028
    Northampton Blvd. to Guelph Line
    Anticipated construction start early 2028

    Watch for: The Region says night work is part of the project and it gives advance notice of lane shifts and work-hour changes.

    Source: Halton Region, Dundas Street Improvements

  3. What QEW and Highway 403 work is planned in Burlington?

    The Ontario Ministry of Transportation's highway program, as of May 29, 2026, lists six Burlington projects, shown in the table. Bridge rehabilitation at the QEW/403/407 and Fairview Street interchanges (Phase 2) started in 2026 with a target completion of 2029, and work on the Highway 403 King Road underpass was underway with a 2026 target. Resurfacing of the QEW from Guelph Line to Third Line, bridge work at Waterdown Road and Lemonville Road, and resurfacing of Highway 403 from the QEW/403/407 interchange to Highway 6 are planned to start in 2027, with targets of 2028-2029.

    QEW/403/407, Fairview St. interchanges, Phase 2
    Bridge rehabilitation · started 2026, underway · target completion 2029
    Highway 403, King Rd. underpass
    Bridge rehabilitation · started 2024, underway · target completion 2026
    QEW, Guelph Line to Third Line
    Resurfacing · planned start 2027 · target completion 2028-2029
    Highway 403, Waterdown Rd. and Lemonville Rd.
    Bridge rehabilitation · planned start 2027 · target completion 2028-2029
    Highway 403, QEW/403/407 interchange to Hwy 6
    Resurfacing · planned start 2027 · target completion 2028-2029
    QEW/403/407 (Freeman interchange), Phase 3
    Bridge and culvert rehabilitation · planned start 2028-2029 · target completion not available

    Watch for: The Province says the timing of projects is subject to change based on funding, approvals, design, property and construction requirements.

    Source: Government of Ontario, Ontario Highway Program: southern Ontario projects (as of May 29, 2026)

City of Burlington road and bridge work

3 questions
  1. When will the Walkers Line renewal be finished?

    The City is renewing Walkers Line from the North Service Road to Berton Avenue in 2026 and 2027, with curb and sidewalk work, a cycle track, storm sewer repairs, resurfacing, streetlights, traffic signals and noise wall replacement. Between the North Service Road and Upper Middle Road, the boulevard work is expected to be complete in 2026 and repaving has been moved to spring 2027; that final milling and paving will be done at night over about three weeks because of traffic volumes. Work from Upper Middle Road to Berton Avenue is scheduled for spring to fall 2027.

    Source: City of Burlington, Walkers Line Renewal

  2. What is the New Street bridge project at Tuck Creek?

    The City is replacing the New Street bridge at Tuck Creek, with road resurfacing and storm culvert replacement, on a schedule the City gives as June 2025 to November 2026 and calls tentative. During bridge construction one lane in each direction is maintained on New Street, with signed pedestrian detours, and the City asks drivers to plan alternative routes or allow extra time.

    Source: City of Burlington, New Street Bridge Replacement at Tuck Creek

  3. When will the Spruce Avenue road work be done?

    The City of Burlington and Halton Region are working in the Spruce Avenue area (Spruce Avenue, Goodram Drive, Shoreacres Place and Mackay Court) in 2026 and 2027: road, curb, sidewalk, storm sewer and streetlight work by the City and watermain replacement on Spruce Avenue by the Region. The City says the watermain work has been delayed by supply chain issues and utility conflicts, which pushes the road work on Spruce Avenue to 2027, with road works expected to be completed in spring or summer 2027.

    Watch for: The City says disrupted areas will be temporarily repaired for the winter.

    Source: City of Burlington, Spruce Avenue Area Minor Reconstruction

Official sources and contacts

6 official pages
City of BurlingtonMetrolinx Burloak Drive UnderpassThe official page this guide’s first answer is checked against. The office that runs the service has the final word on a case of your own.Open burlington.ca
Who to contact
City of Burlington road construction projects
905-335-7777 · city@burlington.ca
Halton Region (Regional roads)
311, or 905-825-6000

Sources

  1. City of BurlingtonMetrolinx Burloak Drive UnderpassRetrieved November 26, 2026
  2. Halton RegionDundas Street ImprovementsRetrieved November 26, 2026
  3. Government of OntarioOntario Highway Program: southern Ontario projects (as of May 29, 2026)Retrieved November 26, 2026
  4. City of BurlingtonWalkers Line RenewalRetrieved November 26, 2026
  5. City of BurlingtonNew Street Bridge Replacement at Tuck CreekRetrieved November 26, 2026
  6. City of BurlingtonSpruce Avenue Area Minor ReconstructionRetrieved November 26, 2026

Every answer on this page traces to one of these documents.

Last checked 6 official pages from City of Burlington, Halton Region, Government of Ontario