Burlington signs agreement with Alinea to explore an arena and second ice pad at 1200 King Road
A City memo says Burlington and Alinea Land Corporation have a memorandum of understanding to explore community facilities on the 1200 King Road site, led by an event centre arena. Nothing has been approved, and terms are confidential.
The update
- The City of Burlington and Alinea Land Corporation have established a memorandum of understanding to explore community facilities on the 1200 King Road development site, a memo in the November 20, 2026 Council Information Package says.
- The focus is an event centre arena with a secondary ice facility. A community centre with aquatics or basketball, conference space and parking are secondary and would likely come later, if at all.
- No facility, size or design has been approved. Staff are to report back with a funding strategy, partnership model and implementation plan, targeted for the second quarter of 2027.
Why it matters. It is the first formal step with the site's developer toward a possible new arena in Burlington, though any spending still needs a Council decision.
What the City announced
The City of Burlington and Alinea Land Corporation have established a memorandum of understanding to support exploring community facilities on the 1200 King Road development site, according to a memo from the Chief Administrative Officer's office released in the November 20, 2026 Council Information Package.
The memo says it is for information only. The agreement relies on direction Council gave on June 23, 2026 in report CAO-01-26, when Council told the Chief Administrative Officer to proceed with a detailed due diligence phase and report back before any capital or financial commitment. Council also told staff to follow a recommendation in a confidential appendix to that report, and the memo says the agreement was signed in that context.
What is being explored
- Main focus
- Event centre (arena) with a secondary ice facility
- Also in scope
- Community centre, including aquatics and/or basketball facilities
- Also in scope
- Conference or multi-purpose space
- Also in scope
- Parking facility
The memo says the partnership work is focused mainly on the arena and the second ice pad. The other facilities are secondary considerations at this stage and, if pursued, would likely be phased in later, subject to due diligence and an independent business case.
It is explicit that no facility, configuration or scale has been approved. Whether any of the facilities go ahead, and in what form, will depend on the due diligence, a business case and a funding strategy that may include money from other levels of government.
What is confidential
The terms of the memorandum of understanding are confidential. The memo discloses only that it has been signed by the City and Alinea Land Corporation, and attaches none of its terms. It does not give a date of signing or any cost figure.
What happens next
Staff are continuing the detailed due diligence: confirming capital and operating costs and operating models; talking with prospective partners, funding contributors, possible operators and other service delivery partners; updating a community-level economic analysis; evaluating financing options; and preparing to support a funding request to senior levels of government. They are to report back to Committee and Council with a recommended funding strategy, partnership model and implementation plan, targeted for the second quarter of 2027 or earlier if possible.
Spotted an error? We keep the URL, update the timestamp and record the change. Our corrections policy.