Millcroft Greens: groundwater wells go in the week of November 30; Phase 1 site work waits on a City agreement

Groundwater monitoring wells are expected on part of the Millcroft golf course the week of November 30, the City says. Site preparation for the approved first phase cannot start until a pre-servicing agreement is finalized.

The update

  • The developer told the City that groundwater monitoring wells are expected to be installed northwest of the clubhouse during the week of November 30, 2026; the work is weather dependent and should take one day.
  • Phase 1 site preparation, including topsoil removal, creek realignment and a retaining wall, cannot begin until a pre-servicing agreement with the City is finalized; no start date has been confirmed.
  • Millcroft Greens has appealed Council's September 29 refusal of the Phase 2 applications to the Ontario Land Tribunal, the City says.

Why it matters. Residents around the Millcroft golf course in Ward 6 will see equipment on site soon, and the City has set out what work is coming, when it is allowed and who to call about it.

What happens the week of November 30

The City of Burlington says the developer of Millcroft Greens, at 2155 Country Club Dr. in Ward 6, has told it that groundwater monitoring work is expected on a portion of the golf course northwest of the clubhouse during the week of November 30, 2026. A contractor will install groundwater monitoring wells, with equipment entering through the golf course parking lot. The City says the work is weather dependent, is expected to take one day, and does not require City approvals or development agreements, because property owners can investigate site conditions on private land.

The notice is on a new City page, posted November 27 under the Mayor's and Ward 6 councillor's news, that gathers updates on both phases of the project. The City says Millcroft Greens, as the lead on this private development, will also give advance notice of future site activity, including timing and potential impacts such as noise.

Phase 1: what work is coming, and when

Phase 1 was approved by the Ontario Land Tribunal. The City says work has not yet begun on site and a construction start date has not been confirmed. Site preparation will be done under a pre-servicing agreement that the City is finalizing with the developer, and work is expected to begin shortly after that agreement is finalized. The City says it will post an update confirming when construction starts.

  • Site preparation, including erosion and sediment controls, and setting up equipment
  • Removing topsoil and moving soil
  • Creek works, including realigning the creek
  • Changes to the existing irrigation reservoir and a new irrigation watermain within the creek block
  • A retaining wall
Rules and mitigation the City lists for this phase
Construction hours
7 a.m. to 7 p.m., Monday through Saturday; no work on Sundays or statutory holidays without prior permission from the City's by-law enforcement
Noise and vibration
Contractor bound by the City's noise and nuisance by-law; real-time vibration monitoring by the developer's qualified professional
Dust and mud
Mud mats at each site access, water truck and dust suppressant when needed, regular street cleaning
Traffic
Traffic management measures, road sweeping and flushing
Questions about site work
Millcroft Greens: info@millcroftgreens.com, 289-208-7543

Underground servicing, private roads, home construction and landscaping need further approvals. The City notes that some requirements, such as Conservation Halton permits for the creek works, come from other agencies, which are responsible for their own enforcement.

Phase 2: under appeal

Council refused the Phase 2 Official Plan amendment and draft plan of subdivision on September 29, 2026. The City says it has received an appeal of that refusal to the Ontario Land Tribunal, and that Millcroft Greens' appeal will address the criteria for those approvals. The Province's zoning orders do not override Council's refusal, the City says, but they establish that residential uses are permitted on those lands if the applicant meets the technical requirements. The page does not give a hearing date.

The date

Groundwater monitoring wells installed (week of November 30)
Week of 30 Nov · Northwest of the clubhouse; equipment enters through the golf course parking lot; weather dependent, about one day. · Milestone

Dates as this story states them, each traced to its sources.